Aurora Solar Farm, located on land at Twelve Acre Farm, OX29 4BH, and was approved by the West Oxfordshire District Council in early 2020.
Engie Fabricom has been appointed as the main construction contractor for the project. They will have the day to day responsibility for the construction of the project and will manage a collection of sub-contractors to undertake the work.
• S278 Bellmouth Works - 100% complete
• Marking out Internal Roads - 100% complete
• Installation of Internal Roads - continuing, 75% complete
• Install Offices/Canteens/Welfare at Site Compound - 100% complete
• Site Signage - continuing, 95% complete
• Installation of Fencing- continuing, 95% complete
• Frames - Pile Installation -100% complete
• Mounting Structure Installation - continuing, 95% complete
• DC String and Main AC Cabling and Trenching - continuing, 80% complete
• Install Inverters and Connection - continuing, 80% complete
• Foundations - continuing, 95% complete
• Install Transformers - continuing, 90% complete
• Install DNO Station - continuing, 95% complete
• Install Customer Substation - continuing, 50% complete